     What should the batching plant staff usually do when the concrete mixing plant working is finished? Is the power off sequence correct? To develop good production practices, it is pretty important to concrete mixing plant a long-term normal operation.
    End of the operation, close the following switches:

    1. pump power switch;
    2. host power switch;
    3. total control switch;
    4. additive pump switch;
    5.Air compressor switch
    6. After the completion of the operation within two hours, the batch plant mixing host all contact with the concrete parts cleaning and not allowed to accumulate a period of time to assault the phenomenon in one time.